Name of Power Station Capacity (in MW) Status
Mohammadpur Power Station 3 X 3.1 RMU work of Mohammadpur Power Station is completed on 21/07/2013.
Pathri Power Station 3 X 6.8 MW RMU work of Pathri Power Station is completed on 30/08/2014.
Khatima Power Station 3 X 13.8MW RMU work of Khatima Power Station is completed on 26/09/2016.
Tiloth (MB-1) 3 X 30 Agreement executed for RM&U in Dec. 2016. Reverse Engineering of one unit completed. Design and Engineering Works are in progress. The M&U is scheduled to be completed by Dec. 2021.
Dhalipur HEP 3 X 17 Agreement executed for M&U in April 2017. Reverse Engineering of one unit completed. Design and Engineering Works are in progress. The M&U is scheduled to be completed by June 2021.
Dhakrani HEP 3 X 11.25 Financial Evaluation of bids is in progress.
Chilla HEP 3 X 36 Financial Evaluation of bids is in progress.
Kulhal HEP 3 X 10 Hon’ble UERC has not given approval of RMU. Matter is pending with Hon’ble APTEL for considering approval of RMU.
Ramganga HEP 3 X 66 Hon’ble UERC has not given approval of RMU. Matter is pending with Hon’ble APTEL for considering approval of RMU.