S.no Name of Power Station Capacity (in MW) Status
1. Mohammadpur Power Station 3X 3.1 RMU work of Mohammadpur Power Station is completed on 21/07/2013.
2. Pathri Power Station 3X 6.8 MW RMU work of Pathri Power Station is completed on 30/08/2014.
3. Khatima Power Station 3X13.8MW RMU work of Khatima Power Station is completed on 26/09/2016.
4. Tiloth (MB-1) 3 x 30 Agreement executed for RM&U in Dec. 2016. Reverse Engineering of one unit completed. Design and Engineering
Works are in progress. The M&U is scheduled to be completed by Dec. 2021.
5. DhalipurHEP 3 x 17 Agreement executed for M&U in April 2017. Reverse Engineering of one unit completed. Design and Engineering
Works are in progress. The M&U is scheduled to be completed by June 2021.
6. Dhakrani HEP 3x11.25 Financial Evaluation of bids is in progress.
7. Chilla HEP 3x36 Financial Evaluation of bids is in progress.
8. Kulhal HEP 3x10 Hon’ble UERC has not given approval of RMU. Matter is pending with Hon’ble APTEL for considering approval of RMU.
9. Ramganga HEP 3x66 Hon’ble UERC has not given approval of RMU. Matter is pending with Hon’ble APTEL for considering approval of RMU.
 
 